Shambaugh & Son contracted with Fort Wayne Community Schools as Prime mechanical contractor to perform the Physical Plant Improvements at various schools throughout the city of Fort Wayne.

Mechanical Construction Project Description:

  • Performed mechanical improvements at seven (7) various schools, including:
    • Boiler room renovations
    • Laboratory renovations
    • Restroom renovations
    • Rooftop unit installations
    • Classroom HVAC renovations
    • Swimming pool HVAC renovations

Shambaugh & Son’s $1.5 million contract on this retrofit project included the following scope of work:

Commercial Mechanical & HVAC Installation Services

  • Mechanical
    • Organized, scheduled, and completed on-time improvements at the seven (7) schools
    • Demolished and re-installed boilers in three (3) schools
    • Scheduled and supervised all trades, including MEP (mechanical, plumbing, electrical), concrete, finishes, and temperature controls
    • Installed nineteen (19) 200,000 Btu high efficiency boilers
    • Installed two (2) split system rooftop units
    • Change out of pumps and hydronic accessories
    • Change out of plumbing fixtures, lab faucets, and piping